Topre is an automotive stamping plant. Forty-foot racks of process piping were installed. We also did some prefabrication for the mechanical room. Due to the prefabrication, on-site installation of the mechanical room just took over one day. Installation went very quickly for the overhead piping out in the plant; installed within hours because hangars were already up.
Fabrication
Topre
- MarketIndustrial
- StatusComplete
- Contract Size$10,000,661.92
- OwnerTopre America
- CM / GCMarker Construction
- LocationSpringfield, OH
- EngineerGresham Smith and Partners (Phase 1&2)Collaborative Design LTD (Phase 7)
- SystemsHVAC, Plumbing, Fire Protection