TP Implements New Fabrication Method – Fully Prefabricated Mechanical Rooms

News

Projects

Share

TP Implements New Fabrication Method – Fully Prefabricated Mechanical Rooms

In today’s ever-changing construction environment, TP Mechanical continues to adapt and innovate. We know the challenges of large-scale construction projects, and for over thirty years we’ve answered them with our market-leading, quality-driven fabrication division. As a leader in the fabrication industry, TP continues to push the envelope with new technology and capabilities. We are proud and excited to announce we are now building and pre-assembling entire mechanical rooms in our fabrication facilities.

There are many benefits to pre-assembling a mechanical room offsite. TP’s Distribution Center is an extremely safe and controlled environment where production continues even when there is inclement weather. With a portion of the project’s manpower shifting from the jobsite to our distribution center, onsite assembly requires less time while still achieving a seamless installation process. This strategy also ensures we have eliminated any and all issues before the field installation occurs. This high-level prefabrication allows for us to avoid jobsite delays and meet strict deadlines, which is a continued priority for all our projects.

TP Mechanical was thrilled to utilize this strategy for a new central energy plant at Big Walnut Schools with general contractor, Gilbane Building Company. This energy plant is equipped to provide a total of 1500 tons cooling capacity, twenty-four million BTU’s of heating, which supports the over 350,000 square feet for the new Big Walnut High School and Prairie Run Elementary.

To ensure the installation of piping and equipment went as effortlessly and fast as possible, TP built the entire mechanical room in our 100,000 square foot distribution center. This energy plant consists of (4) six million BTU boilers, (3) 500-ton chillers, hydronic pumps, (2) air separators, (2) expansion tanks, a chemical feeder, (3) 1500-gallon cooling towers, a makeup water system and more.

The mechanical room was completely pre-assembled while the energy plant structure was simultaneously being built.  Once the building was dried-in, the pre-assembled portion of the mechanical room was broken down into segments, then shipped to the jobsite to allow for an efficient and expedited installation. From disassembly to reassembly on-site, the process was performed in a period of four days.

To learn more about TP’s fabrication division, visit https://www.tpmechanical.com/fabrication/. Discover how our team offers unparalleled skill with sophisticated software to generate innovative, customized solutions for your primary challenges.